Renovation of industrial floor in a printing plant
The production area of this printing plant needed to have the floor renovated as it was damaged by previous operations. Working in an operational environment required some precautions: the industrial instruments and production machines were in place so no dust could be introduced in the plant. The customer needed a fast drying solution to limit the operating losses
The existing floor was shot-blasted and primered with a sanded weberfloor 4712 epoxy primer to increase the adhesion to the substrate. The industrial screed weberfloor 4630 was pumped from outside the building in a thickness of 10 mm with over 150m hose length. The printing machines started working less than 24 hours after application of the floor screed. In the future a resin coating may be applied.